ALVISO, CALIFORNIA

South San Francisco Bay Shoreline Levee Construction Reaches 1-3 Project

PROJECT DESCRIPTION

The South San Francisco Bay Shoreline Levee Construction Reaches 1-3 Project site, near Alviso, California, is the location of historical salt harvesting ponds. Undertaken to mitigate flood risk and restore tidal wetland areas of the Bay, the project required ~1.7 miles of levee degrade and levee reconstruction along sensitive San Francisco Bay Shoreline under contract to USACE. Ancillary to construction of the flood risk management levees, the $150+ million project required temporary railroad crossing construction, several miles of temporary earthen cofferdams, over one mile of continuous sheet pile cofferdams, and numerous water control and pedestrian structures. Shallow groundwater, seepage, soft soils including both young and old “Bay Mud,” and environmentally sensitive habitats characterize the site. The project required an extensive dewatering system infrastructure comprised of
sumps, pumps, conveyance systems and cofferdams to remove surface water and depress groundwater within the levee footprint to allow bottom-up construction of new levees. Strict adherence to environmental regulations to protect the natural habitat within the project boundaries was required by the USACE and regulatory agencies. Comprehensive environmental requirements addressed
protecting Endangered Species Act-listed bird species and the salt march harvest mouse and complying with stringent dewatering discharge monitoring requirements. The project required the import of ~75,000 cubic yards of material for temporary earthen cofferdams and an additional ~600,000 cubic yards of material as levee fill and 35,000 cubic yards of topsoil following degrade of over 400,000 cubic yards.

The South San Francisco Bay Shoreline Levee Construction Reaches 1-3 Project site, near Alviso, California, is the location of historical salt harvesting ponds. Undertaken to mitigate flood risk and restore tidal wetland areas of the Bay, the project required ~1.7 miles of levee degrade and levee reconstruction along sensitive San Francisco Bay Shoreline under contract to USACE. Ancillary to construction of the flood risk management levees, the $150+ million project required temporary railroad crossing construction, several miles of temporary earthen cofferdams, over one mile of continuous sheet pile cofferdams, and numerous water control and pedestrian structures. Shallow groundwater, seepage, soft soils including both young and old “Bay Mud,” and environmentally sensitive habitats characterize the site. The project required an extensive dewatering system infrastructure comprised of sumps, pumps, conveyance systems and cofferdams to remove surface water and depress groundwater within the levee footprint to allow bottom-up construction of new levees. Strict adherence to environmental regulations to protect the natural habitat within the project boundaries was required by the USACE and regulatory agencies. Comprehensive environmental requirements addressed protecting Endangered Species Act-listed bird species and the salt march harvest mouse and complying with stringent dewatering discharge monitoring requirements. The project required the import of ~75,000 cubic yards (CY) of material for temporary earthen cofferdams and an additional ~600,000 CY of material as levee fill and 35,000 CY of topsoil following degrade of over 400,000 CY. The project is slated to be completed in July of 2025.

PROJECT LOCATION & ACCESS

The Reach 1 levee, running north-south, is bound by Alviso Marina Park and Pond A-12 and the crossing of Union Pacific Railroad (UPRR); and Reach 2/3, running east-west, is bound by UPRR and Artesian Slough and Ponds A16 and the New Chicago Marsh. The site has limited access from two locations; Reach 1 was from Hope Street and the Alviso Marina and Reach 2/3 was from Grand Boulevard at the Don Edwards Wildlife Education Center. Two areas of the project area are tidally influenced. The Alviso Slough in Reach 1 and the Artesian Slough in Reach 2,3.

The Reach 1 levee, running north-south, is bound by Alviso Marina Park and Pond A-12 and the crossing of Union Pacific Railroad (UPRR); and Reach 2/3, running east-west, is bound by UPRR and Artesian Slough and Ponds A16 and the New Chicago Marsh. The site has limited access from two locations; Reach 1 was from Hope Street and the Alviso Marina and Reach 2/3 was from Grand Boulevard at the Don Edwards Wildlife Education Center. Two areas of the project area are tidally influenced. The Alviso Slough in Reach 1 and the Artesian Slough in Reach 2,3.

LEVEE DEGRADE & RECONSTRUCTION

Levee degrade operations for Reach 1 employed large excavators and on- and off-road haul trucks and resulted in generation of 140,000 cubic yards of material, of which 132,000 cubic yards was unsuitable for levee reconstruction and disposed of within the Pond A12 disposal site. Reach 1 levee reconstruction employed 225,000 cubic yards of imported levee fill, 35,000 cubic yards of imported trench fill, and 7,000 cubic yards of specified reuse materials for dike reconstruction. Site restoration employed 7,000 cubic yards of imported topsoil. Reach 2/3 degrade operations generated 223,000 cubic yards of excavated material that was also largely disposed of in the Pond A12 disposal area. Reconstruction efforts used large dozers, active and passive compactors using intelligent compaction technology, and motor graders and required 17,000 cubic yards of specified semi-compacted fill, and 343,000 cubic yards of select fill to reconstruct the levee. Restoration of the Reach 2/3 area employed 25,000 cubic yards of topsoil material. The engineered levees have a crest elevation ranging from 15 to 17 feet, a minimum crest width of 16 feet, and 3H:1V side slopes. The Reach 1 levee’s finish surface included rodent fencing on the landside and high-performance turf reinforcement mat (HPTRM) underlain by heavy non-woven geotextile on the water side (Pond A12) to enhance stability and erosion protection of the levee slope surface to protect it from future storm surges. On Reach 2/3, both slope surfaces were finished with the rodent fencing. The rodent fencing was covered with topsoil and hydroseeded with native grasses. In both project locations, the protective coverings were secured with percussion-driven earth anchors and 18-inch steel washer pins. The access road, on top of the levee, was surfaced with a minimum of eight inches of CalTrans Class 2 Aggregate Base graded with a three percent crown.

Levee degrade operations for Reach 1 employed large excavators and on- and off-road haul trucks and resulted in generation of 140,000 CY of material, of which 132,000 CY was unsuitable for levee reconstruction and disposed of within the Pond A12 disposal site. Reach 1 levee reconstruction employed 225,000 CY of imported levee fill, 35,000 CY of imported trench fill, and 7,000 CY of specified reuse materials for dike reconstruction. Site restoration employed 7,000 CY of imported topsoil. Reach 2/3 degrade operations generated 223,000 CY of excavated material that was also largely disposed of in the Pond A12 disposal area. Reconstruction efforts used large dozers, active and passive compactors using intelligent compaction technology, and motor graders and required 17,000 CY of specified semi-compacted fill, and 343,000 CY of select fill to reconstruct the levee. Restoration of the Reach 2/3 area employed 25,000 CY of topsoil material. The engineered levees have a crest elevation ranging from 15 to 17 feet, a minimum crest width of 16 feet, and 3H:1V side slopes. The Reach 1 levee’s finish surface included rodent fencing on the landside and high-performance turf reinforcement mat (HPTRM) underlain by heavy non-woven geotextile on the water side (Pond A12) to enhance stability and erosion protection of the levee slope surface to protect it from future storm surges. On Reach 2/3, both slope surfaces were finished with the rodent fencing. The rodent fencing was covered with topsoil and hydroseeded with native grasses. In both project locations, the protective coverings were secured with percussion-driven earth anchors and 18-inch steel washer pins. The access road, on top of the levee, was surfaced with a minimum of eight inches of CalTrans Class 2 Aggregate Base graded with a three percent crown.

PROJECT STRUCTURAL ELEMENTS

The project scope included the demolition and reconstruction of existing water control structures, dikes, pedestrian boardwalks, and overlooks. The concrete water control structure on Dike B on Reach 1, designed to move water from Pond A13 to Pond A12, was demolished and replaced in a different location. For Reaches 2/3, MOJV replaced an existing siphon to manage the water levels in New Chicago Marsh to meet project environmental requirements. The 16-foot-tall reinforced concrete water control structure was constructed with flared wing walls that match the levee’s slope. This structure includes a 48-inch reinforced concrete pipe (RCP) that runs from Pond A16 through the levee, and discharges into New Chicago Marsh that is metered using a new 48-inch slide gate. The wooden pedestrian boardwalk was replaced-in-kind and provides pedestrian access from the marsh to the top of the levee.

The project scope included the demolition and reconstruction of existing water control structures, dikes, pedestrian boardwalks, and overlooks. The concrete water control structure on Dike B on Reach 1, designed to move water from Pond A13 to Pond A12, was demolished and replaced in a different location. For Reaches 2/3, MOJV replaced an existing siphon to manage the water levels in New Chicago Marsh to meet project environmental requirements. The 16-foot-tall reinforced concrete water control structure was constructed with flared wing walls that match the levee’s slope. This structure includes a 48-inch reinforced concrete pipe (RCP) that runs from Pond A16 through the levee, and discharges into New Chicago Marsh that is metered using a new 48-inch slide gate. The wooden pedestrian boardwalk was replaced-in-kind and provides pedestrian access from the marsh to the top of the levee.

DEWATERING & WATER TREATMENT SYSTEMS

To maintain dewatered conditions within the levee degrade an reconstruction area footprint of both reaches during construction, we designed and constructed two comprehensive freestanding dewatering systems, inclusive of sheet pile and earthen cofferdams; dewatering sumps; and dewatering conveyance piping and holding tanks, along with semi-automated treatment, and a discharge system to hydrostatically control surface and groundwater levels.

Earthen cofferdams that served as temporary haul roads were constructed on the eastern and western
sides of the Reach 1 levee and on the south side of the Reach 2/3 levee. Interlocking steel sheetpile
and earthen cofferdams were constructed on the northern and southern sides of Reach 2/3, respectively. Approximately 700 linear feet (LF) of sheet pile cofferdam was installed using a 400K lb. crane at the southwest side end of the reach in Alviso Sough, which is tidally influenced. Another 1000 LF of sheetpile cofferdam was installed at the northern side of the Reach 1 levee in Pond A13. Nearly a mile of continuous interlocked sheetpile wall was installed in Pond A16 at Reach 2/3 using a small crane feeding sheets to the floating pile driver. This sheetpile wall functioned as a cofferdam in this area of deeper water. Dewatering sumps were installed surrounding both the Reaches 1 and 2/3 levee footprints between the sheet pile and earthen cofferdams. We installed HDPE piping, treatment, and discharge systems that permitted the water to be conveyed from the dewatering sumps through the main header pipes routed to two on-site water treatment plants, one at each reach. Groundwater was extracted with a network of more than 100 sumps set ~two feet below the lowest degrade elevation for
that area. The modular, expandable, treatment systems were designed to treat the groundwater to meet the San Francisco Regional Water Quality Control Board (SFRWQCB) requirements.

Water conveyed from the dewatering pumps through the main header pipes was routed to the treatment systems to remove entrained sediment or other contaminants using sedimentation in four 18,000-gallon weir tanks per system. The system had been designed with additional treatment stages that could be used as needed for polishing. Treatment system design included physical filtration using 500-gallons-per-minute (gpm) sand filters and 10-micron bag filters and enhanced turbidity reduction by the addition of a fully biodegradable chitosan-based flocculant. Second and third stage treatment was not required to meet SFRWQCB discharge requirements.

Each of the two treatment systems included a treatment trailer that housed in-line water quality parameter monitors to measure and record influent and discharge effluent pH, dissolved oxygen (DO), temperature, turbidity, and flow. Sampling ports allowed for influent and effluent sample collection for laboratory analyses to determine concentrations of dissolved sulfide and nutrients (e.g., nitrogen, phosphorous) in effluent. The modular treatment systems were sized to treat 500
gpm at each reach and were expandable in 500 gpm increments for use during the wet weather season to accommodate peak flows, if necessary.

To maintain dewatered conditions within the levee degrade and reconstruction area footprint of both reaches during construction, we designed and constructed two comprehensive freestanding dewatering systems, inclusive of sheet pile and earthen cofferdams; dewatering sumps; and dewatering conveyance piping and holding tanks, along with semi-automated treatment, and a discharge system to hydrostatically control surface and groundwater levels.

Earthen cofferdams that served as temporary haul roads were constructed on the eastern and western sides of the Reach 1 levee and on the south side of the Reach 2/3 levee. Interlocking steel sheetpile and earthen cofferdams were constructed on the northern and southern sides of Reach 2/3, respectively. Approximately 700 linear feet (LF) of sheet pile cofferdam was installed using a 400K lb. crane at the southwest side end of the reach in Alviso Sough, which is tidally influenced. Another 1000 LF of sheetpile cofferdam was installed at the northern side of the Reach 1 levee in Pond A13. Nearly a mile of continuous interlocked sheetpile wall was installed in Pond A16 at Reach 2/3 using a small crane feeding sheets to the floating pile driver. This sheetpile wall functioned as a cofferdam in this area of deeper water. Dewatering sumps were installed surrounding both the Reaches 1 and 2/3 levee footprints between the sheet pile and earthen cofferdams. We installed HDPE piping, treatment, and discharge systems that permitted the water to be conveyed from the dewatering sumps through the main header pipes routed to two on-site water treatment plants, one at each reach. Groundwater was extracted with a network of more than 100 sumps set ~two feet below the lowest degrade elevation for that area. The modular, expandable, treatment systems were designed to treat the groundwater to meet the San Francisco Regional Water Quality Control Board (SFRWQCB) requirements.

Water conveyed from the dewatering pumps through the main header pipes was routed to the treatment systems to remove entrained sediment or other contaminants using sedimentation in four 18,000-gallon weir tanks per system. The system had been designed with additional treatment stages that could be used as needed for polishing. Treatment system design included physical filtration using 500-gallons-per-minute (gpm) sand filters and 10-micron bag filters and enhanced turbidity reduction by the addition of a fully biodegradable chitosan-based flocculant. Second and third stage treatment was not required to meet SFRWQCB discharge requirements.

Each of the two treatment systems included a treatment trailer that housed in-line water quality parameter monitors to measure and record influent and discharge effluent pH, dissolved oxygen (DO), temperature, turbidity, and flow. Sampling ports allowed for influent and effluent sample collection for laboratory analyses to determine concentrations of dissolved sulfide and nutrients (e.g., nitrogen, phosphorous) in effluent. The modular treatment systems were sized to treat 500 gpm at each reach and were expandable in 500 gpm increments for use during the wet weather season to accommodate peak flows, if necessary.

ENVIRONMENTAL REQUIREMENTS

Located in sensitive habit with avian, aquatic, and terrestrial Endangered Species Act (ESA)-listed species present, MOJV implemented measures to comply with USFWS, USEPA, and NOAA Fisheries requirements. An on-site biological monitor was present during all work activities during the nesting
season to oversee the habitats that could be occupied by federally listed species to look for individuals
potentially impacted by construction. When depredation of special status species by their natural predators was identified, MOJV worked with the USACE and biological monitors to support the removal of at-risk and abandoned eggs to a licensed facility for incubation and reintroduction back to the refuge. Completion of the long expanse of sheet pile cofferdam in Pond A16 within Reach 2/3 isolated a significant section of the pond, stranding fish. MOJV engaged fisheries biologists to seine the segregated areas for fish both prior to unwatering and then again as the water level dropped, which naturally congregated the schools of fish allowing further herding and recovery. Approximately 20,000
fish of various species were captured, inventoried, and returned to the still live section of Pond A16.

Located in sensitive habit with avian, aquatic, and terrestrial Endangered Species Act (ESA)-listed species present, MOJV implemented measures to comply with USFWS, USEPA, and NOAA Fisheries requirements. An on-site biological monitor was present during all work activities during the nesting season to oversee the habitats that could be occupied by federally listed species to look for individuals potentially impacted by construction. When depredation of special status species by their natural predators was identified, MOJV worked with the USACE and biological monitors to support the removal of at-risk and abandoned eggs to a licensed facility for incubation and reintroduction back to the refuge. Completion of the long expanse of sheet pile cofferdam in Pond A16 within Reach 2/3 isolated a significant section of the pond, stranding fish. MOJV engaged fisheries biologists to seine the segregated areas for fish both prior to unwatering and then again as the water level dropped, which naturally congregated the schools of fish allowing further herding and recovery. Approximately 20,000 fish of various species were captured, inventoried, and returned to the still live section of Pond A16.

MEETING PROJECT CHALLENGES

Hydrogen Sulfide. Discovering previously unidentified hydrogen sulfide (H2S) gas and associated impacted soils affected all aspects of the project even though MOJV is a seasoned environmental contractor. When MOJV construction and on-site safety personnel identified this distinctive rotten egg (H2S) odor, we knew immediately what it was. Work was stopped and the USACE was immediately notified. H2S is a colorless, flammable, and highly toxic gas with a distinctive odor that can be immediately dangerous to life and health (IDLH) at 100 parts per million (PPM). A byproduct of anaerobic digestion, or decomposition, of organic matter, H2S may be present in Bay Muds, particularly
at the bottom of ponds, in low-lying areas, and in sediments, which is what was experienced on this
project. The team reacted promptly to this hazard and, working with USACE safety staff, amended the project HASP and field protocols to comply with USACE EM 385-1-1 and other safety requirements including H2S threshold levels established by American Conference of Government Industrial Hygienists (ACGIH). MOJV implemented full scale, all hands H2S Awareness Training, deployed personal air monitors with alarms on all staff, installed data loggers on site, and conducted full-face respirator fit testing. Trained safety personnel, overseen by a Certified Industrial Hygienist (CIH), were
on site to monitor conditions and ensure that specific safety protocols were followed and that appropriate levels of PPE were donned when warranted by conditions, such as upgrading from Level D to Level C PPE.

Weather Impacts. The area was impacted by two consecutive winters with 100-year storm events, which had an outsize impact on the earthen site, halting site activities during heavily saturated periods with ponded water and later delaying the remobilization of personnel and equipment to restart the project tasks. Weather and the above noted H2S significantly impacted the project schedule.

Change in the Mudline. An early bathymetric survey on the north side of Reach 2/3 revealed that the mudline was lower than identified in the project plans. MOJV and our subcontractors worked together to further investigate the impact and the USACE was notified. Under a changed condition, the sheet pile design was updated to meet the actual grade, which required the research, procurement, and installation of longer sheets placed further offshore to account for the extended slope of the final grade caused by the lower mudline. This design change resulted in significantly more water to be managed during the unwatering process and additional area to be dewatered long term. By moving the sheet pile alignment further offshore, installation from shore was no longer viable so the installation methods were redesigned to accommodate sheet pile driving from specially designed small barges (Flexifloats) supporting the pile driving equipment on water.

Site Conditions. Shallow groundwater, seepage, and soft soils, including both young and old “Bay Mud,” are present at the site making equipment selection and the civil grading operations challenging. Construction on Bay Mud sites is difficult because of the soil’s low strength and high compressibility. The Reach 1 design did not include degrade to the higher strength “old Bay Mud” except within the inspection trench area and therefore by design, required additional consolidation time for pore pressure to dissipate. This was tracked using settlement plates and closed-loop surveys as well as installation and data recovery from seven vibrating-wire piezometers. The consolidation period following stage 1 levee completion (at elevation 12) took place during construction of Reach 2/3, with the MOJV team returning to complete the Reach 1 levee upon government acceptance.

Live Railroad Crossing. Following 1.5 years of planning and coordination, MOJV was able to construct a robust railroad crossing on the existing UPRR main line that bifurcated the project site. This is a live commercial and commuter line where trains are permitted to travel at speeds up to 79 miles per hour. Attaining all the necessary approvals to construct the crossing was exceedingly challenging. Constructing the crossings was done with exceptional care and continuing coordination with the railroad entities. Certified railroad flaggers helped manage the movement of trucks and other vehicles on both approaches for each reach. Once constructed, inspected, and approved, MOJV worked carefully with our subcontractors to make sure that similar care was taken during use of the crossing
throughout the project. Thousands of loads of Reach 2/3 degrade material traversed this crossing safely to access the Pond A12 disposal area. As required during both construction and use of the crossing, a protocol was established to detect any rail deflection or settlement. This was implemented daily and later weekly by a professional land surveyor. To date, no exceedances on the actual rail settlement have been observed. MOJV will continue to use this crossing until completion of the project, when the temporary crossing will be removed.

Public Interaction to Maintain Safety. The project is in a very popular area for hiking, mountain biking, and wildlife photography. MOJV worked carefully with stakeholders and the USACE to develop strategies to communicate that public access was not allowed, through media and onsite messaging. On-site workers were trained to engage pedestrians and bike riders and professionally and respectfully encourage them to remain outside of this large construction area. This strategy proved very effective. To further support public safety, MOJV worked with a security company to develop and install a strategic, security camera system that was monitored during non-work hours. A live interface was available when anyone from the public entered the construction zone. This approach was very effective in informing those who wanted to enter the site that the area was closed. This ongoing challenge has lessened with time passing and our public education and awareness efforts, and no significant
incidents have occurred.

Import Material. Most excavated material was not suitable for constructing the engineered levee, requiring fill to be imported from an offsite borrow source. The USACE provided 106,000 cubic yards of levee fill in two stockpile areas adjacent to Reach 1. Additional levee fill was required to meet both geotechnical and environmental specifications and was secured by MOJV and brought to the site as needed to reconstruct both levees. MOJV adjusted the design of the haul route to Reaches 2/3 to eliminate a sharp turn across traffic by haul trucks, improving safety and lessen impact to the existing road surface that was beginning to fail.

Regulatory and Public Scrutiny. As part of the largest wetlands restoration on the West Coast, the project is in an area that is environmentally sensitive, is popular with the public, and has been monitored by numerous stakeholder groups. Regulatory and stakeholder groups include Santa Clara Valley Water District, the City of San Jose, U.S. Fish & Wildlife Service, California Department of Fish and Wildlife, California State Coastal Conservancy. San Francisco Bay Bird Observatory, and others. MOJV proactively supported the USACE in its communications with regulatory and stakeholder groups
by providing clear, up-to-date information; attending meetings; and addressing concerns.

Project Highlights

  • Degrade and re- construction of nearly 2 miles of levee for flood risk management
  • Installed a water structure on Dike B to move water from Pond A13 to A12 on Reach 1
  • Constructed a 48” RCP water control structure on Reach 2/3 for water management
  • Installed and maintained 2 fully operational dewatering/water treatment systems with around 50 pumps for each system
  • Saved over 20,000 fish at Pond A16

Project Awards

  • 2026 Outstanding Environmental Engineering Project, awarded by the ASCE SF Section, San Jose Branch
  • 2025 Coastal Zone Management and Stewardship Award, awarded by the Floodplain Management Association (FMA)

Project Details

START DATE:

August 2021

END DATE:

November 2025

VALUE:

$153.7M