El Paso, Texas. Odin continues to make major strides on the American Canal Lower Reach Replacement Project, a critical infrastructure initiative ensuring reliable water delivery for agricultural irrigation and municipal supply in El Paso. The American Canal is the primary conduit through which the El Paso County Water Improvement District #1 (EPCWID) provides irrigation water to more than 58,130 acres of farmland in the El Paso Valley. Additionally, El Paso Water treats up to 70,000 acre-feet of Rio Grande surface water from the canal for the city’s potable water supply. Since being placed in service in 1938, the canal has deteriorated, requiring phased reconstruction to maintain its serviceability and enhance water flow efficiency.
The project scope includes demolishing approximately 3,215 linear feet of the existing canal and replacing it with 2,518 linear feet of 24-foot span by 12- to 14-foot rise arch concrete culverts, along with 510 linear feet of 24-foot by 15-foot-deep concrete U-channel to connect to the College Arroyo Overchute. To improve the canal’s hydraulic performance, the design deepens the channel by three feet, increasing its flow capacity from 1,200 cubic feet per second (cfs) to 1,535 cfs. Additional project elements include the installation of manholes, safety and accessibility features such as ramps, safety ladders, safety cables, and handrails, as well as the design and construction of a secant pile wall and tiebacks to manage earth retention and groundwater control.
First Construction Season Accomplishments
Despite the project’s limited construction window, Odin has kept the project on schedule. The first construction season has seen the successful placement of 13 arch culvert sections, allowing El Paso Water to proceed with its planned replacement of the Upper Valley Outfall 30-inch force main sewer line crossing the canal. Other major milestones include:
- Completion of 511 feet of 24-foot-wide, 15-foot-deep U-channel
- Construction of downstream headwalls on both the landside and levee side of the canal
- Demolition and deepening of the existing canal using 10,000 lb. hammers to address subsurface rock
- Design and implementation of a robust dewatering system, successfully keeping the work area dry and operational
- Installation of 1,056 secant piles and 1,680 CY of seal slab
What’s Ahead
As Odin moves forward, upcoming work will focus on installing additional culvert sections, finalizing the remaining U-channel, and continuing secant pile wall construction to address complex geologic and hydrologic conditions.
“Odin and it’s subcontractor stakeholders have showed teamwork, flexibility, and employed aggressive construction execution measures to overcome multiple challenges to keep this project on schedule through Construction Season 1, which sets the stage for a successful Construction Season 2 and ultimate completion of the project,” stated Ed Martinez, Director of Project Management for the American Canal project.
The project remains on track to meet its phased completion goals while ensuring minimal disruption to water deliveries.
Recognizing Excellence
Executing a project of this scale within seasonal constraints requires meticulous planning and an extraordinary commitment from the entire project team. Odin’s crews have worked tirelessly, operating 24/6 to keep the project progressing. Their dedication, expertise, and problem-solving mindset have been instrumental in overcoming challenges such as groundwater management, rocky excavation conditions, and the logistical demands of heavy infrastructure placement.
We appreciate the dedication and expertise of our subcontractors, whose contributions have been instrumental in executing critical aspects of the project. Thank you, Baker Concrete, Bauer Foundations, Orduno, Griffin Fluid Management, Genco Fabrication, and Contech Engineered Solutions.
By maintaining an aggressive construction schedule and implementing innovative solutions, Odin is not only restoring a vital waterway but also enhancing its long-term functionality for the communities and industries that rely on it.
For more information about the American Canal Lower Reach Replacement Project, visit https://odinenv.com/american-canal/.
About Odin
Odin has an award-winning focus on protection and preservation. Our team is empowered to provide stability and reliability to communities across the nation through Environmental Remediation, Heavy Civil & Geotechnical Construction, Habitat & Wetland Construction, and Emergency & Disaster Service projects. Odin has become a communal ally through a commitment to safety, quality, collaboration, and community.