Lake Oroville, California
Loafer Point Boat Ramp Facility, Stage II (Site 10)
PROJECT DESCRIPTION
Odin recently completed the Loafer Point Boat Ramp Facility Stage II Project on Lake Oroville, California. The $6,000,000 project encompassed 13.5 acres and increased the boat launching capacity at Lake Oroville by adding a four-acre parking lot leading to a 785-foot-long, six-lane boat ramp, which can be accessed when lake levels are at or below 805 feet elevation. This project had an aggressive schedule to meet milestones dates considering the entire project is below the Ordinary High- Water Mark on Lake Oroville. Work was performed outside the typical construction season to take advantage of low seasonal lake elevation.
This large civil construction project was designed as a balanced earthwork project with nearly 140,000 cubic yards, cut to fill. The project required extensive pre-planning and construction logic sequencing to create safe access to excavation and fill areas. The site was challenging because of wet soil conditions and abrupt topographic elevation changes that created steep ascent and decent approaches for heavy equipment and trucks. Considerable planning was required to establish productive, but more importantly, safe on-site haul routes. Concurrent with grading, all fill slopes were armored with geotextile fabric and 14,000 tons of rock slope protection facing. Hardscape construction included forming and placing approximately 5,400 cubic yards of 4,000 pounds per square inch concrete with 411,000 pounds of reinforcing steel underlain by 6,400 tons of drain rock and nearly 8,000 tons of aggregate base. The final product is a showcase six-lane wide, 785-foot- long, V-grooved boat ramp extending to elevation 705 which is accessed by a finished and striped four-acre parking facility with 180 trailered parking spaces.
Odin worked in collaboration with the Department of Water Resources’ Oroville Project Headquarters and the Department of Parks and Recreation team to complete the project on schedule and meet the final milestone date of March 31, 2021. The project was completed safely with no incidents or lost time accidents.
Project Highlights:
- Completed 140,000 CY of cut and fill excavation
- Constructed a 4-acre concrete parking lot and pipe gates
- Implemented erosion and sediment controls BMPs per the SWPPP; adjusted SWPPP BMPs as necessary to accommodate changes in construction progress
- Formed and placed 5,400 CY of 4,000 psi concrete with reinforcing steel 175K CY backfill
- 2021 Outstanding Climate Change Project, awarded by the ASCE Sacramento Section