Lassen, Plumas, Siskiyou, Tehama, and Trinity Counties, California

Dixie Fire Emergency Structural Debris and Hazard Tree Removal Services

PROJECT DESCRIPTION

Odin and a joint venture partner were awarded a $68,000,000 contract to provide Emergency Structural Debris and Hazard Tree Removal Services to the California Department of Resources Recycling and Recovery (CalRecycle) from five fire-impacted counties (Lassen, Plumas, Siskiyou, Tehama, and Trinity)
following multiple, “non-complex” fires in July through October 2021. The so-called Dixie Fire was the largest of the fires and burned 963,309 acres in total. The Dixie fire was named for the creek where it
started and the first fire to have burned across the crest of the Sierra Nevada. Following emergency proclamations and Executive Orders in 2021, California’s Consolidated Debris Removal Program was implemented to clean up destroyed structures and hazardous trees that resulted from the fires. The operation was funded by the Federal Emergency Management Agency (FEMA) under Public Assistance private property debris removal (PPDR) requirements. Additional State of California special funding covered operational costs not funded by FEMA. In compliance with FEMA Public Assistance requirements, the State of California’s third-party environmental consultant in conjunction with the Incident Management Team (IMT) was responsible for leading individual property assessments;
overseeing compliance with regulatory requirements; setting background and cleanup levels; and collecting samples for analysis to ensure that soil cleanup levels were achieved by debris removal
efforts. The Odin team worked closely and cooperated with the environmental consultant as well as with utility companies, state government agencies, and other contractors to minimize impacts and delays.

Prior to field mobilization, Odin prepared a site- specific Health and Safety Plan (HASP) for the work in compliance with OSHA standard 29 CFR Part 1910.120, Hazardous Waste Operations and Emergency Response (HAZWOPER). The HASP specified worker protection, including personal protective equipment (PPE), air monitoring, and other worker safety measures. All workers were trained and briefed on the HASP and the hazards and procedures for onsite work. Given that ash has the potential to contain elevated levels of heavy metals and asbestos, Odin crews set up exclusion zones around debris removal sites and wore “Level C” PPE. Air monitoring was conducted continuously by Odin to monitor worker safety; asbestos, silica, and metals (antimony, arsenic, barium, beryllium, cadmium, chromium, cobalt, copper, lead, manganese, molybdenum, nickel, selenium, silver, thallium, vanadium, and zinc) were monitored. Aggressive dust control measures required that fire-related debris be always wet and hauled to the landfill wrapped in plastic to ensure that no hazardous materials were released. Further, Odin’s crews cleaned tires and equipment on site so that no dirt or mud was tracked onto the public right of way.

Odin’s work was completed in compliance with the State’s Environmental Protection Plan (EPP) developed to ensure that the structural debris removal and hazard tree removal functions were compliant with all local, state laws, and Federal laws. Stormwater and erosion control measures included deployment of stormwater best management practices (BMPs) such as straw wattles and spray mulch after debris removal.

Following initial property reconnaissance and assessments conducted cooperatively by CalRecycle’s
Assessment and Monitoring (A&M) contractor and Odin, Odin conducted structural debris removal. Structural debris removal tasks included knocking down chimneys and partial walls; collecting, consolidating, removing, and properly disposing of asbestos-containing materials; felling, processing, and removal of potentially dangerous trees; removal of vehicles to either a central consolidation and inspection or directly to recycling, per direction of CalRecycle. Odin employed crews consisting of equipment operators, laborers, and traffic control personnel. Each crew was equipped with an excavator, front end loader, skid steer, and water truck. Operations were conducted 12 hours per day, six days per week to meet schedule requirements. Waste streams were segregated, managed, and disposed in compliance with regulatory requirements. Waste stream handling included:

• Hauling asbestos containing material (ACM) to an approved ACM disposal site.

• Transporting excavated hazardous fire debris to an approved landfill (lined facility).

• Crushing and consolidating metals, including burned vehicles, and trucking them to an approved bulk metal recycler.

• Hauling removed concrete to an approved concrete recycler.

When soil test results were above the cleanup goals set by the State of California, Odin re-scraped
those parcels an additional six inches to remove contaminated soils.

Hazard tree removal, in compliance with Forest Practice Rules, followed structural debris removal to prevent felling trees into hazardous ash and debris. Odin conducted hazard tree removals following tree
risk assessments by a certified arborist. Tree removal consisted or felling hazard trees and removing limbs and tops on site. They were further processed at a vegetative debris consolidation site; chipped slash was used as mulch for erosion control.

To support the challenges of the remote operations, Odin set up a temporary 12-acre site in Chester, CA that includes the following facilities:

• Basecamp for over 125 workers.

• Multi-acre laydown yard for storage and staging of equipment and materials.

• Wood processing and reduction center including chippers, grinders, and a log deck.

• Metal processing and reduction center including shredders and crushers for processing bulk metals into portable bales.

The ongoing project, scheduled for completion in July 2022, has presented numerous challenges. The high elevations, extreme terrain, and difficult access have created obstacles and safety concerns that Odin has successfully managed by thorough preplanning and the on-site engagement of our team of health and safety experts. Examples of Odin’s ability to address significant challenges are illustrated below.

• High-elevation weather has been our largest uncontrollable hurdle; back-to-back early winter storms covered our work area with ice and multiple feet of snow. Odin has adjusted crew and equipment deployment to match access as snow melts to keep the project moving.

• The global supply shortage has affected the availability of trucks to work on the operation. However, Odin’s excellent working relationships with local trucking firms has allowed us to overcome this hurdle.

• The main haul route (HWY 70) was closed for the first two months of the project following a landslide. Because of our operational flexibility and relationships with our haulers, end use facilities, and landfills, we were able to reroute our entire trucking operation around the major closure to keep the waste streams moving.

• The work has been conducted during the COVID-19 pandemic, which has required safety precautions that have been evolving with the pandemic. Odin is experienced with COVID-19 prevention and enforcement at employer-provided lodging/housing locations for remote worksites where base camp operations are needed to support field workers.

CLIENT AWARDS

• 2022 Outstanding Environmental Engineering Project of the Year, awarded by the ASCE Sacramento Section

Project Details

START DATE:

October 2021

END DATE:

July 2022

VALUE:

$78.6M

CLIENT CONTACT

Stephen Eto, 916.693.7429, stephen.eto@calrecycle.ca.gov

error: Content is protected !!