OCEANO, CALIFORNIA
Arroyo Grande Creek Channel Emergency Levee Rehabilitation
PROJECT DESCRIPTION
Odin was selected to strengthen the levee system along the Arroyo Grande Creek Channel in Oceano, California to prevent future flooding events and protect the surrounding communities. The need for improvement was highlighted in early 2023, when multiple breaks in the levee, overtopping, and seepage caused flooding in neighborhoods and farmlands. The narrow project site lies between an environmentally sensitive area on one side and modular homes or agricultural fields on the other. The sensitive habitat for threatened and endangered species, including the California red-legged frog, required ongoing protective measures during construction. The project consisted of constructing four separate hydraulic barriers composed of slag cement-cement bentonite (SCCB) slurry through the centerlines of the north and south levees at locations that were damaged or of concern. The hydraulic barriers were needed to meet slope stability and seepage design criteria and reduce the potential for seepage-related damage to the levee during a flood or high-water event. The barriers were constructed by excavating a vertical walled slurry trench along the existing levee centerline and placing SCCB slurry within the trench. The four barrier segments totaled approximately 4,600 linear feet and ranged in depth from 20 to 25 feet below the crest of the levee. The minimum 2.5-foot-wide SCCB barriers were overlain by biaxial Type 2 geogrid reinforcement and backfilled with six inches of compacted Class 2 aggregate base, and covered with felted fabric reinforcement and five inches of Class 3 aggregate base, which formed the roadway surface atop the repaired sections of levee spanning the crest width. The minimum width of the levee crest is eight feet but varies within the project limits. The construction method for the hydraulic barriers allowed for the continued function of the levee as a flood control structure through the winter construction season. The project was safely completed on time and within budget.
The project team overcame numerous challenges, including:
- Narrow Project Area With Limited Access.Between an environmentally sensitive area and homes or agricultural fields, the project area was so narrow there was no room to turn trucks or equipment around. As the trench was excavated and SCCB placed, all spoils were directly loaded with a PC490 or PC336 excavator into haul trucks, which were required to back down the levee crown road to exit the site and properly dispose of spoils onsite. Odin was required to ensure access by farmers to their lands and implemented traffic control measures to ensure the safety of haul truck traffic, local farmers, and the county as it conducted its maintenance of the levees.
- Access to Water.As there was no readily available water source, Odin purchased water needed to prepare the SCCB slurry from farmers with adjacent land. Access to and use of this water source could not impact farming operations, requiring Odin to obtain water during other than construction hours, at times in the middle of the night.
- Limited Staging Areas. Separate staging areas were required as the batch plant was moved three times as construction progressed. The small staging areas were leased from farmers and housed the batch plant, silos for storge of bulk materials, a slurry pond, equipment, and temporary storage of spoils. Traffic control measures included staging area ingress and egress. Ongoing coordination and management of materials in these small areas contributed to the success of the project.
- Storm Drain Pipes within the Levee Prism.On one of the segments, there were three metal storm drain pipes ranging from 12 to 30 inches in diameter as well as 3.5-inch PVC pipes that were protected in place during construction. The equipment operators had to carefully excavate around these obstructions, taking care to cause no damage.